The project involves placing 66 logs and 15 rootwads from the road into side channels off mainstem Rock Creek with an excavator. It also involves knocking or pulling 32 trees (18-24” diameter) over with an excavator and moving them into the stream channel. The trees may be up to 150’ away from the nearest excavator access and may need to be dragged with a cable to get them to the excavator and stream channel. Six existing logs in the stream will also need to be moved within the channel. The project also involves excavating out the mouth of up to four side channels. The access for some of the sites is complicated and involves moving the logs up to 2000’ from the road to the site with multiple stream crossings including mainstem Rock Creek.